items or functions. The contractor shall support use of this information in any first flight readiness or aircraft certification effort required by the contract.
5.3.6 Analysis.
The contractor shall complete detailed analysis to determine the effects of the environments on each avionics subsystem. The contractor shall analyze the design for compliance with the reliability, maintainability and diagnostics requirements of the contract. The contractor shall analyze avionics impacts on the system level FMECA.
5.3.7 Tests and demonstrations.
The contractor shall complete development tests for durability and design life of any high risk items (new technology, extreme environment, innovative packaging scheme, etc). The contractor shall define test procedures or other verification methods for environmental qualification and durability or life tests. The contractor shall define equipment acceptance tests.
5.3.8 Life management.
The contractor shall define the impact on integrity of any anti-tamper protection methods applied to avionics items. The contractor shall perform updates based on program needs.
5.4 Phase IV: Verification and production (complete by delivery).
Phase IV includes test, inspection, or analysis to verify that the released avionic design meets all integrity requirements. These tasks are performed in conjunction with efforts under the manufacturing and quality integrity program to verify that production quality is maintained.
5.4.1 Planning and coordination.
The contractor shall document any changes to system, subsystem and component integrity requirements in the AIMP and document them appropriately. The contractor shall document results of verification tests, analyses and demonstrations. The contractor shall develop and document a plan for tracking any life-limited or scheduled maintenance items within the avionics system.
5.4.2 Design criteria.
No major or specific tasks are identified for this element during this phase.
5.4.3 Characterizing the environment.
No major or specific tasks are identified for this element during this phase.
5.4.4 Characterizing materials and components.
The contractor shall identify and document all lead-free solder usage, identify associated risks, and document/implement any mitigations required.
The contractor shall verify Parts Integrity (including sources) via approved procedures and methodologies, shall identify known risks, and shall implement risk mitigations.